*** ISO 9001:2015 Quality Management System *** Hexatech Engineering Engineering Engineering Engineering Engineering Sdn. Bhd. *** Provision Of Supply, Installation, Maintenance And Servicing Of Mechanical And Electrical Systems *** ISO 9001:2015 Quality Management System *** Hexatech Engineering Engineering Engineering Engineering Engineering Sdn. Bhd. *** Provision Of Supply, Installation, Maintenance And Servicing Of Mechanical And Electrical Systems *** ISO 9001:2015 Quality Management System *** Hexatech Engineering Engineering Engineering Engineering Engineering Sdn. Bhd. *** Provision Of Supply, Installation, Maintenance And Servicing Of Mechanical And Electrical Systems *** ISO 9001:2015 Quality Management System *** Hexatech Engineering Engineering Engineering Engineering Engineering Sdn. Bhd. *** Provision Of Supply, Installation, Maintenance And Servicing Of Mechanical And Electrical Systems *** ISO 9001:2015 Quality Management System *** Hexatech Engineering Engineering Engineering Engineering Engineering Sdn. Bhd. *** Provision Of Supply, Installation, Maintenance And Servicing Of Mechanical And Electrical Systems *** ISO 9001:2015 Quality Management System *** Hexatech Engineering Engineering Engineering Engineering Engineering Sdn. Bhd. *** Provision Of Supply, Installation, Maintenance And Servicing Of Mechanical And Electrical Systems *** ISO 9001:2015 Quality Management System *** Hexatech Engineering Engineering Engineering Engineering Engineering Sdn. Bhd. *** Provision Of Supply, Installation, Maintenance And Servicing Of Mechanical And Electrical Systems *** ISO 9001:2015 Quality Management System *** Hexatech Engineering Engineering Engineering Engineering Engineering Sdn. Bhd. *** Provision Of Supply, Installation, Maintenance And Servicing Of Mechanical And Electrical Systems *** ISO 9001:2015 Quality Management System *** Hexatech Engineering Engineering Engineering Engineering Engineering Sdn. Bhd. *** Provision Of Supply, Installation, Maintenance And Servicing Of Mechanical And Electrical Systems *** ISO 9001:2015 Quality Management System *** Hexatech Engineering Engineering Engineering Engineering Engineering Sdn. Bhd. *** Provision Of Supply, Installation, Maintenance And Servicing Of Mechanical And Electrical Systems *** ISO 9001:2015 Quality Management System *** Hexatech Engineering Engineering Engineering Engineering Engineering Sdn. Bhd. *** Provision Of Supply, Installation, Maintenance And Servicing Of Mechanical And Electrical Systems
 

Home   QMS   Context Of Organization    Leadership    Planning    Support    Operation    Performance Evaluation   Improvement    Site Map

QMS-PRO-07 Issue No. 1 Revision No. 1 Effective 01 Jan 2023   

 
 

8.     Operation

 

8.1   Operational planning and control.

 

         In Hexatech Engineering’s operation, corporate planning is carried out solely by Managing Director (MD)

         after taken into consideration of all views made by manager in charge:

 

               * overall company policies with regards to production management.

       

              * overall management policies.

            

              * overall resources such as: materials, human resource, finance, and etc.

 

              * quality, health and safety policy.

            

              * quality objectives.

            

              * procedures and business processes, which includes verification, monitoring

                 and inspection activities.

      

        * records required to provide evidence that the project engineering and implementation

           activities are carried out.

           

              * operations planning and monitoring of services including day-to-day running of

                 project engineering and implementation, human resources recruitment and administration

                 of resources.

             

                * annual activities to meet quality objectives and Hexatech Engineering operational requirements.

                 

                >>>  Annex G   -  Project Management Framework  

                         Annex M -   Hexatech Engineering ISO9001:2015 Annual Activity Time Chart

 

8.2   Requirements for products and services.

        

         8.2.1   Customer communication - land telephone line, handphone, correspondence,

                      email, meeting, visit, etc.

        

         8.2.2   Determining the requirements for product and services.

  

                     In Hexatech Engineering’s project engineering and implementation provision, customer

                     requirements are recorded for the following services:

       

                    *  Engineering services.

                    *  Project implementation services.

                    *  Maintenance services.            

                                   

        In determining the customer requirements the respective manager in charge

        will ensure to determine the necessary processes as follows:

 

        Managing Director (MD)

        >>> OCS-PRO-01   Risk Management Procedure

                OCS-PRO-02   Organizational Knowledge Procedure

                OCS-PRO-03   Health, Safety & Environment Procedure

 

        Contracts Manager (CM)

        >>>  CPD-PRO-01   Tender & Contracts Procedure

                 CPD-PRO-02   Material Requisition & Purchasing Procedure

                 CPD-PRO-03   Outsourced Vendor Control Procedure

                 CPD-PRO-04   Customer Verification of Purchased Products & Services Procedure

              

              Designer Engineer (DE)

              >>>  ENG-PRO-01   Design and Development Procedure

                       ENG-PRO-02   Control of Technical Drawings Procedure

                       ENG-PRO-03   Control of Inspection, Measuring & Testing Equipment Procedure

                                                  

        Project Manager (PM)

         >>>  Annex G         Project Management Framework

                  PD-PRO-01    Project Engineering & Methodology Procedure

                  PD-PRO-02    Project Planning Procedure

                  PD-PRO-03    M&E Project Installation Works Procedure

                  PD-PRO-04    Project Inspection, Testing & Commissioning Procedure

                  PD-PRO-05    Stock Control & Transfer of Materials Procedure

                  PD-PRO-06    Customer Supplied Materials Handling Procedure

                  PD-PRO-07    Project Handover & Demobilization Procedure

                  PD-PRO-09    Method Statement For M&E Projects

 

         Maintenance Manager (LM)

         >>>  PD-PRO-08    Maintenance Works Procedure

                  PD-PRO-09    Method Statement For M&E Projects

 

        Human Resource Manager (HRM)

        >>>   HRA-PRO-01  Job Descriptions

                  HRA-PRO-02  Recruitment Procedure

                  HRA-PRO-03  Awareness, Training & Competency Procedure

 

         Administration Executive (AE)

        >>>   AD-PRO-01   Correspondence & Drawings Handling Procedure

                  AD-PRO-02   Management Meetings Procedure

                  AD-PRO-03   Disclosure Protection Administration Procedure

                  AD-PRO-04   Office Equipment Maintenance Procedure

 

              ISO Manager (IM)

              >>>  QSA-PRO-01   Control of QMS Documented Information Procedure

                       QSA-PRO-02   Customer Satisfaction Procedure

                       QSA-PRO-03   Customer Complaints Procedure

                       QSA-PRO-04   Internal Quality Audit Procedure

                       QSA-PRO-05   Analysis of Data & Process Improvement Action Procedure

                       QSA-PRO-06   Corrective Action Procedure

                      

                     

       8.2.3   Review of the requirements for M&E engineering and implementation servicecs.

 

                    8.2.3.1  The manager in charge is basically responsible to review the requirements

                                   of the respective services provided to the customers.  The review is

                                   conducted to ensure high service levels are achieved.

                                                  

                    8.2.3.2  Where there are cases of additional product and service requirements,

                                   this shall be communicated to the Managing Director (MD) for further

                                   allocation of resources.

 

         8.2.4   Changes to requirements for products and services. 

 

                     Any changes to the requirements for products and services are reviewed by

                     ISO Manager (IM) and put forward to Managing Director (MD) for approval

                     before the changes are implemented.

     

                     >>>   QSA-PRO-01           Control of QMS Documented Information Procedure

                               QSA-REC-QDCR     QMS Document Change Register

                               QSA-REC-QDCN    QMS Document Change Notice

                               QSA-REC-DDL        QMS Document Distribution List

                               QSA-REC-RM         Read Memo

                               QSA-REC-QDIAR   QMS Documented Information Archiving Register

                               QSA-REC-QDIAL    QMS Documented Information Archive Label

                              

8.3   Design and development of project engineering and implementation services.

 

         Not Applicable Clause:

 

         MS ISO9001:2015 Clause 8.3 Design and Development of Products and Services is not applicable

         to the scope of Hexatech Engineering Quality Management System.

 

         Should the above requirement become relevant in the future; the company will develop the

         necessary and relevant procedures for inclusion in the QMS.

 

         The provision of Hexatech Engineering's products and services are tailored to meet customers' requirement

         which had been predetermined with approved design and development criteria.

 

8.4   Control of externally provided processes, products and services.

 

         8.4.1   General.

 

                      In support of Hexatech Engineering's project  and implementation provision, all externally

                      provided resources and specialized services are procured by Purchasing Executive

                      (PURE) with the use of the Purchase Order.

 

                      To procure an externally provided item or services, the manager in charge or

                      appointed Hexatech Engineering personnel shall submit a Material Requisition Form (MRF)

                      for approval before the Purchase Order (PO) are issued to external providers.

 

                      >>>  CPD-PRO-02         Material Request & Purchasing Procedure

                               CPD-REC-MRF     Material Requisition Form

                               CPD-REC-MOAF  Memorandum Of Approval Form

                               CPD-REC-ALT       Memorandum Of Approval Log

                               CPD-REC-PO        Purchase Order

                              

         8.4.2   Type and extent of control.

 

                     All incoming purchased items are subjected to a physical check upon receipt

                     by the project implementation personnel.  Items that do not comply to

                     specifications are rejected and communicated to the respective suppliers

                     for corrective actions or replacement.

 

                     >>>  PD-PRO-04             Project Inspection, Testing & Commissioning Procedure

                              PD-REC-ITP            Inspection & Test Plan

                              PD-REC-RFMRIR   Request For Material Receiving Inspection Register

                              PD-PRO-05             Stock Control & Transfer of Materials Procedure

                              PD-REC-SC             Stock Card

                              PD-REC-SIF            Stock Issue Form

                              PD-REC-MTF         Material Transfer Form

 

         8.4.3   Information for external providers.

 

                     All Purchase Order (PO) for intended procurement of externally provided

                     resources related to the M&E engineering and implementation services must

                     contain adequate information on the product or service such as specifications,

                     grade, class, size, duration, job scope, etc.

 

                     All POs will be verified by the the Departmental Manager and approved by the

                     Managing Director (MD) and the issuance of the POs will be effected upon

                     receipt of approval from MD.

 

                     All new and existing external providers are evaluated on a yearly basis. The

                     evaluation criteria are stipulated in the vendor evaluation form. The evaluation

                     is carried out by the manager in charge of the respective services (coordinated

                     by PURE).  

 

                     The yearly evaluation of external providers will determine the eligibility of

                     the external providers to be register into the List of Approved Vendors.  Should

                     the evaluation is unsatisfactory, the blacklisting of the external provider shall

                     be effected in accordance to the outsourced vendor control procedure.

 

                     Record of the evaluation and the Approved Vendor List (AVL) is maintained by

                     PURE.  

 

                     >>>   CPD-PRO-03       Outsourced Vendor Control Procedure

                               CPD-REC-VRAF   Vendor Registration & Approval Form

                               CPD-REC-AVL     Approved Vendor List

                               CPD-REC-VPEF   Vendor Performance Evaluation Form

                               CPD-REC-VPER  Vendor Performance Evaluation Report

        

8.5   M&E engineering and implementation of product and service provision.

 

         8.5.1   Control of M&E product and service provision.

 

                     The provision of project and maintenance services are planned and

                     controlled at the respective manager in charge.

                    

                     Each manager in charge is primarily responsible for the efficiency of their 

                     designated services as detailed out in their respective job descriptions.

            

         8.5.2   Identification and traceability.

 

                      Hexatech Engineering shall apply suitable means of identification throughout its provision of

                      M&E engineering and implementation services, such as:

 

a)      Each work request for M&E engineering and servicing shall be identified

         by a project reference to be recorded by the Project Manager (PM).

        

b)       Materials, equipment and tools used in the provision of any on-site

          servicing shall be traceable to outsourced vendors.

 

c)       The identification of each service status with respect to monitoring and

           measurement conducted shall be identified by the PE on work inspection

           checklists, field service reports, delivery orders, test reports, testing and

          commissioning certificates, or other appropriate records.

                     

         8.5.3   Property belonging to customers or external providers.

 

                     It is very seldom that Hexatech Engineering is involved in handling of customer property in

                     the conduct of its M&E engineering and implementation services, however, should

                     there be a need to use customer property, then, Hexatech Engineering shall exercise care with

                     customer property while it is under its control or being used by its appointed

                     specialist vendor. 

 

                     Hexatech Engineering shall identify, verify, protect and maintain customer property provided

                     for use.   Occurrence of any customer property that is lost, damaged or otherwise

                     found to be unsuitable for use shall be recorded and reported to the customer.
 
                     >>>   PD-PRO-06       Control Of Customer Supplied Materials Procedure
                               PD-REC-CSML  Customer Supplied Materials List

 

         8.5.4   Preservation.

                     

                     The respective assigned Hexatech Engineering project personnel shall be responsible to

                     preserve the conformity of their installed equipment as per given workscope.

                     This preservation shall include identification, handling and protection of all

                     materials, equipment and tools received from vendors including those

                     supplied by the customer (if any).  

 

                     Appropriate mechanical handling equipment shall be used and stored

                     adequately (in case for temporary storage) to prevent damage,

                     deterioration or loss.

            

         8.5.5   Post-delivery activities.

 

                     The post-delivery activities provided by Hexatech Engineering in terms of warranty

                     provisions, contractual obligations, on-site servicing and supplementary

                     services shall be handled by Project Manager (PM).

 

         8.5.6   Control of changes.

      

                      Hexatech Engineering's manager in charge is responsible to address any changes to the

                      requirements made by the customer.  Such changes shall be informed to the

                      Project Manager (PM) and the manager in charge is to take necessary steps

                      to fulfill the requirement of the customer.

 

8.6   Release of products and services.

 

         All Hexatech Engineering personnel involved in M&E engineering and implementation services are

         required to undergo adequate training before being assigned to undertake post project

         activities with the customer.

 

         The release of products and services shall only be conducted after adequate acceptance

          by the customer and proper preservation and packaging of the product are taken before

          delivery to customer.

        

          >>>   PD-PRO-07          Project Handover & Demobilization Procedure

                   PD-REC-WCBOF  Works Completion Buy Off Form

 

8.7   Control of non-conforming outputs.

 

         8.7.1   All non-conforming products and services rendered by Hexatech Engineering are identified,

                     recorded, and analyzed to determine the cause or causes of the

                     non-conformances. Corrective actions are determined and implemented to

                     prevent recurrence of the incident.

 

         8.7.2   The responsibilities, controls and authorities for dealing with the non-conforming

                      products and services are detailed in the control of non-conforming product

                      procedure. Records of the non-conforming product and service and the actions

                      taken are maintained by  ISO Manager (IM).

 

          >>>   QSA-PRO-06       Control of Non-Conforming Product Procedure

                    QSA-REC-NCRL  Non Conformance Report (NCR) Log

                    QSA-REC-NCR    Non Conformance Report (NCR)